Corporate center contractor gets 4-month extension in Milford

By Brian Trompeter

Milford City Council unanimously extended George & Lynch Inc.’s contract for Phase 1 of the Milford Corporate Center to July 10 after snowstorms and utility conflicts delayed the project. The extension comes as the company’s contract reaches nearly $18.9 million following recent change orders for electrical and asphalt work. Council also approved a conditional-use permit for Stone & Sage Holistic Healing and authorized $748,259 for paving, sidewalk, curb, storm-drain and accessibility improvements on seven city streets.

Read More

Wednesday, March 4, 2026

Extra money OK’d for electric, roads at Milford Corporate Center

By Brian Trompeter

Milford City Council unanimously approved nearly $900,000 in change orders March 2 for electrical and asphalt work at the Milford Corporate Center. The largest, a $693,515 request from George & Lynch, will cover electric conduit installation and a bore under Canterbury Road. Another $200,255 will fund milling and overlay work on Canterbury Road. The expenses were already included in the city’s capital improvement plan, with eligible road costs subject to reimbursement through a $5.05 million DelDOT infrastructure grant. The changes bring George & Lynch’s adjusted contract for Phase 1 to $18.88 million.

Read More